Shinkansen line·5 min read

Chūō Shinkansen

中央新幹線

The Chūō Shinkansen is a Japanese maglev line under construction between Tokyo and Nagoya, with plans for a later extension to Osaka. Its initial section runs from Shinagawa Station in Tokyo to Nagoya Station, with intermediate stations in Sagamihara, Kōfu, Iida and Nakatsugawa; following completion of the Tokyo–Nagoya section the line is to be extended through Mie and Nara to Osaka. The line is expected to connect Tokyo and Nagoya in 40 minutes, and eventually Tokyo and Osaka in 67 minutes, running at a maximum speed of 505 km/h. About 90% of the 286 km line to Nagoya will be in tunnels. The route was deliberately chosen to be more direct than the existing Tōkaidō Shinkansen — Plan C, passing under the Japanese Alps (Akaishi Mountains) — because time saved through a straighter alignment was a more important criterion to JR Central than serving intermediate population centres. The line will have a minimum curve radius of 8,000 m and a maximum gradient of 4%, steeper than the 3% ceiling of conventional Shinkansen lines.

Route of the Chūō Shinkansen · Prefectures: MLIT · Tokyo–Nagoya under construction, Nagoya–Osaka planned

History

The project is the culmination of Japanese maglev development pursued since the 1970s. After the Tōkaidō Shinkansen opened between Tokyo and Osaka in 1964, Japanese National Railways (JNR) turned to developing faster maglev technology, and in the 1970s built a 7 km test track for maglev research in Miyazaki Prefecture. Once the desired results had been obtained there, an 18.4 km test track incorporating tunnels, bridges and slopes was built in Yamanashi Prefecture between Ōtsuki and Tsuru. Trains on the Yamanashi test track routinely achieved operating speeds of over 500 km/h, and the track was later extended a further 25 km along the future route of the Chūō Shinkansen to bring its combined length to 42.8 km, with the extension and upgrade work completed by June 2013. JR Central now operates the facilities and research, and the Chūō Shinkansen is intended to extend and incorporate the existing Yamanashi test track.

Government permission to proceed with construction was granted on 27 May 2011, when the Ministry of Land, Infrastructure, Transport and Tourism instructed JR Central — already named as the line's construction and operating entity — to build the line. JR Central had announced in December 2007 that it would fund construction on its own, without government financing. The total cost, originally estimated at 5.1 trillion yen in 2007, escalated to over 9 trillion yen by 2011. The Ministry approved Plan C for construction on 31 October 2014, and construction began on 17 December 2014. Construction of a 25 km tunnel under the southern Japanese Alps commenced on 20 December 2015, reaching roughly 1,400 m below the surface at its deepest point; upon completion it is expected to surpass the 1,300 m-deep Daishimizu Tunnel on the Jōetsu Shinkansen as the deepest tunnel in Japan. The line's high expense is driven largely by the fact that most of it runs underground — about 86% of the initial Tokyo–Nagoya section — with some sections built as deep underground at a depth of 40 m.

The line's opening target has slipped repeatedly because of a dispute with Shizuoka Prefecture, the only prefecture along the Tokyo–Nagoya route to receive no new station. The prefecture expressed concern that water from the Ōi River would leak into the tunnel and lower the river's water level, and in a June 2020 meeting Shizuoka officials denied permission to begin tunnel construction. JR Central announced the following week that opening the Tokyo–Nagoya line in 2027 as previously planned would be 'difficult'. Governor Heita Kawakatsu, re-elected in June 2021 partly on a platform of continued opposition, announced on 2 April 2024 that he would resign, less than a week after JR Central confirmed it could not meet the 2027 target. The ensuing by-election on 26 May 2024 was won by Yasutomo Suzuki, described as a maglev proponent, after which preliminary work was approved and proceeded. In January 2026 Suzuki and JR Central President Niwa signed a letter of agreement under which JR Central would compensate for any decrease in Ōi River water resources without requiring the prefecture to prove the construction caused it, and on 26 March 2026 a Shizuoka special committee approved all 28 environmental conservation measures proposed by JR Central. By the time of the cited revisions, JR Central had said a 2027 opening was impossible and the Tokyo–Nagoya line was not expected to open until at least 2034 (stated 2024), with reports in 2025 pushing the prospect to no earlier than 2035.

The Nagoya–Osaka extension was originally planned to open as late as 2045, a schedule designed to keep JR Central's total debt below its level at the time of privatisation; after the company received a loan from the Japanese government the completion date was brought forward to as early as 2037. The Osaka prefectural government and Kansai-region businesses had raised concerns about the impact of the delayed extension on the Osaka economy, and Kansai politicians called for and received state-backed loans to expedite the line, moving the extension's opening forward by up to eight years.

The Chūō Shinkansen will employ the SCMaglev system developed by JR Central, in which the levitating force is generated between superconducting magnets on the trains and coils on the track; the superconducting coils use a niobium–titanium alloy cooled with liquid helium. The absence of wheel friction allows higher speeds and greater acceleration than conventional high-speed rail. Its rolling stock is the L0 Series. The line traces a chain of maglev test vehicles: on 2 December 2003 a three-car MLX01 set a manned world record of 581 km/h on the Yamanashi test track, and on 26 October 2010 JR Central announced the L0 Series for commercial operation at 505 km/h, which went on to set a manned world record of 603 km/h on 21 April 2015. On 26 March 2020 the Improved L0 Series began operations on the test track — the first to draw power from the track rather than from on-board gas generators.

Timeline

  • 1962JNR sets a goal of linking Tokyo and Osaka (about 500 km) in one hour and turns to frictionless superconducting levitation.
  • 197315 November: the Tokyo-Osaka corridor is designated a basic-plan Shinkansen route under the Nationwide Shinkansen Railway Development Act.
  • 1990November: construction begins on the Yamanashi maglev test line, on the planned route of the Chūō Shinkansen.
  • 1997The 18.4 km initial section of the Yamanashi test line is completed; running tests begin 3 April, and an unmanned run reaches 550 km/h on 24 December.
  • 20032 December: a three-car MLX01 set reaches 581 km/h in a manned run on the Yamanashi test track, certified the world rail speed record the following year.
  • 2007December: JR Central announces it will fund construction of the line on its own, without government financing; total cost is then estimated at 5.1 trillion yen.
  • 201026 October: JR Central announces the L0 Series train type for commercial operation at 505 km/h.
  • 201127 May: government permission to proceed is granted as MLIT instructs JR Central, the named construction and operating entity, to build the line; cost had escalated to over 9 trillion yen.
  • 2013The full 42.8 km Yamanashi test line is completed and testing with the L0 Series service-type trainset begins; extension and upgrade work allowed top-speed running over longer periods.
  • 201431 October: MLIT approves Plan C (under the Japanese Alps) for construction; the Tokyo (Shinagawa)-Nagoya groundbreaking is held on 17 December.
  • 201521 April: on the Yamanashi test track the L0 Series sets a manned world rail speed record of 603 km/h, later certified by Guinness World Records.
  • 201520 December: construction begins on the 25 km tunnel under the southern Japanese Alps, reaching about 1,400 m below the surface at its deepest point.
  • 2020June: Shizuoka Prefecture officials deny permission to begin tunnel construction over Ōi River water concerns; JR Central says a 2027 Tokyo-Nagoya opening is now difficult.
  • 2024March-April: JR Central abandons the 2027 target, with opening not expected before 2034; Governor Kawakatsu announces his resignation on 2 April, and maglev proponent Yasutomo Suzuki wins the 26 May Shizuoka by-election.
  • 2025The Tokyo-Nagoya opening outlook is reported to have slipped to no earlier than 2035 amid rising costs.
  • 2026January: Shizuoka's governor and JR Central sign a water-resources compensation agreement; on 26 March a prefectural special committee approves all 28 environmental conservation measures proposed by JR Central.

Sources